How Saudi Contractors Can Build an Ex Skills Matrix Before Tender Review

Writer: Certify Power House
Certify Power House
Nov 12
6 min read

Saudi clients often check workforce competence during tender review, long before any crew reaches site. A clear Ex skills matrix can tip that review in your favour. It shows the client who does what and which IECEx units each person holds. Better still, most contractors can build one within a few days. This guide shows you how, step by step, with a sample layout you can copy.

Ex skills matrix for Saudi contractors: 5 steps to plan IECEx CoPC units before tender review

Why Tender Teams Ask About Ex Competence

Oil, gas, petrochemical and mining sites across the Kingdom carry large hazardous areas. One wrong install or a missed inspection can lead to a fire. So asset owners want proof that every contractor can staff Ex work safely. Many of them now check that proof at bid stage, not just at the gate.

In practice, this means the technical evaluation may include questions about personnel competence. Some tenders name exact IECEx units for each trade. Others ask for a general competence plan. Either way, a contractor with a clear matrix looks prepared. By contrast, one who promises to "sort it later" looks risky.


What an Ex Skills Matrix Shows

An Ex skills matrix is a simple table of your people, their roles and their IECEx units. It also lists each certificate's expiry date. So a client can see at a glance whether your crew covers every Ex task in the scope. At the same time, it shows you exactly where the gaps are.

Here's a sample layout you can adapt:

Name

Role

Units held

CoPC expiry

Status

Worker A

Electrician

Ex 001, Ex 003, Ex 004

March 2029

Covered

Worker B

Instrument technician

Ex 001, Ex 003

June 2027

Needs Ex 004

Worker C

Ex inspector

Ex 001, Ex 007

January 2027

Renewal due

Worker D

Helper

Site awareness

Not applicable

Covered

Keep the columns short and clear. A tender reviewer should understand the table in under a minute.


Step 1: Pull Every Ex Clause From the Tender

Start with the tender pack. Highlight every line that mentions hazardous areas, Ex equipment or personnel competence. Some clients name exact units, while others describe tasks such as "install Ex equipment" or "inspect Ex installations". Either way, write down each requirement in plain words before you look at your staff list.

Also, check the appendices and the HSE specification. Competence clauses often hide there rather than in the main scope. Missing one clause can leave a gap you only discover at mobilisation.


Step 2: List Roles, Not Just Names

Next, list each Ex role the project needs, such as installer, maintainer, tester or inspector. Then add how many people you need per shift and per site. This view helps you spot shortages early. It also keeps the matrix useful when staff change later, because roles stay fixed while names come and go.

For a shutdown or turnaround job, add a column for peak headcount too. Shutdowns often need far more Ex technicians for a few weeks. So plan that peak separately from your steady crew.


Step 3: Match Current CoPC Holders

Now check who already holds which units. Search each worker on the public IECEx online system to confirm the record and the expiry date. Mark each role as covered, partly covered or open. Be honest here, because the client may run the same search.

While you check, compare names too. The name on the IECEx record should match the passport and the Iqama. If it doesn't, sort it out now, because induction teams will notice later.


Step 4: Plan the Gaps

For every open role, decide whether to train an existing worker or hire someone certified. Training often costs less and keeps your team stable. It also builds loyalty, since staff value employers who invest in their skills. So price the training into your bid and set dates that finish before mobilisation.

When you plan, think about evidence as well. The certification body needs proof of real Ex work for each unit. So start collecting signed job cards and experience letters for each worker now, not the week before the assessment.


Step 5: Present It Clearly

Finally, attach the matrix to your technical offer as a clean one-page table. Add a short note on how and when you'll close any open gaps. Clients value a plan they can read in a minute. That clarity can set your bid apart from competitors who only send CVs.


A Worked Example: A 20-Person Maintenance Crew

Imagine a contractor bidding for a two-year maintenance job at a petrochemical plant in Jubail. The tender asks for 12 electricians, 4 instrument technicians, 2 Ex inspectors and 2 helpers. It names Ex 001, Ex 003 and Ex 004 for the technicians, and Ex 007 for the inspectors.

First, the contractor lists all 20 roles in the matrix. Next, the QA lead checks each current worker online. The result shows 9 electricians fully covered and 3 missing Ex 004. Also, one inspector's CoPC expires in eight months. The helpers need site awareness only.

So the gap plan is short and specific. Three electricians will train for Ex 004 before mobilisation. Meanwhile, the inspector will start renewal next month, with evidence already in hand. The contractor adds dates for both, then attaches the one-page matrix to the bid. As a result, the reviewer sees a crew that's ready, plus a credible plan for the few gaps.


What Tender Reviewers Look For

Reviewers usually scan for three things. First, they check that every Ex role in the scope has a named person or a clear plan. Second, they look at expiry dates against the contract length. Third, they look for realistic dates on any training. If all three look solid, the competence section rarely becomes a problem.


Common Mistakes to Avoid

Even a good matrix can lose marks if it contains avoidable errors. Watch out for these:

  • Listing units without dates: the client can't judge validity.

  • Copying old matrices: people leave and certificates expire.

  • Ignoring support staff: helpers and drivers still enter Ex zones.

  • Vague gap plans: "we will arrange training" doesn't build trust without dates.

  • Mismatched names: the client may not find the record online.


How the Matrix Saves Money Later

A good matrix keeps paying back after the award. When a client adds scope, you can see at once who can take the extra work. When a worker resigns, you know which units you must replace. And when an audit comes, you hand over one clean table instead of chasing files across sites. Over a long contract, those small savings add up to real time and cost.


Keep the Matrix Alive After Award

A skills matrix isn't just a bid document, so once work starts, update it every month. Add new hires, record new units and flag certificates due for renewal. That way, you're always ready for a client audit or a scope change.

Also, share the live matrix with your site supervisors. They can then check quickly who can do which Ex task on each shift. This simple habit cuts the risk of the wrong person working on Ex equipment. It also gives you clean records for your next tender.


Common Questions


How long does it take to build a matrix?

For a small crew, a day or two is often enough. Larger contractors may need a week to gather records from every site. Start early, because missing records take the most time to chase.


Should support staff appear in the matrix?

Yes. List drivers, helpers and office staff who enter Ex areas, even if they only need awareness. That shows the client you've covered every person on site, not just the technicians.


What if a worker's certificate is close to expiry?

Flag it and plan renewal before mobilisation. A CoPC stays valid for five years, and renewal needs proof of recent Ex work. So start gathering evidence a few months ahead.


Can a worker with a CoPC from another country join a Saudi crew?

Yes. The CoPC belongs to a global scheme, so it carries the same weight in the Kingdom. Still, check that the worker's units match the Saudi scope before you add them to the matrix.


Who should own the matrix?

Usually the QA or HSE lead owns it, with input from HR and site supervisors. One clear owner keeps it accurate. Then everyone else knows where to send updates.


Where to Get Support

Need Saudi rules by sector? This guide to IECEx requirements in Saudi Arabia covers each industry and the units it often asks for.


When you're ready to close the gaps, Extrainings runs team batches from its Dammam office and at client sites. The Extrainings team can also review your matrix and suggest units per trade. See the options for IECEx certification in Saudi Arabia and plan training before your next tender.

 
 
 